Construction Projects

Capital Projects

South Denver

  • Construction is underway
  • DOLA Grant awarded.
  • Paving is currently underway.
  • Project completion is mid October 2017.
  • Project extends from Kahil Street south to the city limits.
  • Detours and closures possible through October, your patience is appreciated.
  • Project is complete.

2017 Sidewalk Repair Project

  • Construction starts July 31, 2017.
  • Estimated completion is August 4, 2017.
  • Current list of areas to repair. List is subject to additions. Once the budget is met, the remaining sites will be added to projects to be budgeted in the future.
  • Project is complete.

Factory Circle

Paving Project

  • City Council has elected not to pursue this project at this time due to budget restrictions


  • Mag chloride was applied to stabilize the road and give dust control in Fall 2017.
  • Paving project will go out to bid early 2018.
  • Paving anticipated to start Spring 2018.

9th Street Waterline Replacement

  • Currently under contract.
  • DOLA grant has been received.
  • Estimated project start late September 2017.
  • Road closures between Northrup Avenue and College Avenue (County Road 29.5)
  • Gravity main complete and in service.
  • High pressure line is currently being repaired. Anticipated completion early 2018.

6th Street & Hoover Avenue, 4th Street, 8th Street, and 9th Street Storm Drainage Project

  • Design phase complete.
  • Estimated start late May, 2017.
  • Estimated completion August 2017
  • Project complete.

County Road 23.5

  • Under in-house design phase.
  • Projected for Fall 2017
  • Project includes a regrade and drainage improvements.

County Road 12 Improvements

  • The City of Fort Lupton will be working with Anadarko to repave from South Denver Avenue east to County Road 29. Improvements will include a water line extension, drainage improvements, and widening of the road similar to the South Denver widening project of 2017.
  • Currently pursuing DOLA grant with Anadarko matching funds.
  • In interim, Anadarko is responsible for grading and maintaining this area of road. This is in accordance with previously established agreement with Anadarko.

Non-City Utility Work To find possible construction impacts please contact the utility company conducting the work:

Century Link 1-800-526-3557
Xcel Energy at 1-800-895-4999 
United Power