Construction Projects

Capital Projects

14th Street & Denver and Factory Circle Reconstruction Project (work area map)

  • Work east of Highway 85 is complete.
  • Factory Circle storm and grading improvements are complete.
  • This project, as well as several others, were funded by dollars received from the Department of Local Affairs (DOLA). This project cost $1,894,000; the City Received $750,000 from the grant. The City has received 3 matching DOLA grant funds from 2014 to the present, funding water-sewer projects on 5th St. to 6th St. and Hoover Ave, as well as the new Lift Station at 9th St. and Grand Ave.
  • A paving project for the Factory Circle area is being proposed for next years budget.

County Road 16 Reconstruction

  • Construction will began August, 2016.
  • Curb has been completed.
  • Railroad work will be 09/29 & 09/30
  • Paving will start Monday, October 3.
  • Crews are running ahead of schedule.
  • Anticipated completion mid-November 2016.
  • Map of detours

2016 Paving Project

  • Number of sidewalk/curb/and gutter and paving locations subject to available funds, some will receive spot repairs and others will receive more extensive repairs.
  • Land area survey is complete (including 2nd Street, 3rd Street, 6th Street, and Hoover Avenue).
  • Pre-construction meeting 09/29/16
  • Estimated start October 10, 2016
  • Tentative Schedule of Construction (weather permitting): 10/10-10/21 Hoover Ave from 6th St to 7th St., 10/24-11/05 Hoover Ave from 7th St. to 9th St., 11/07-11/18 6th St. from Fulton Ave to McKinley Ave, 11/21-12-02 2nd St from Fulton Ave to McKinley Ave, 12/05-12/23 3rd St from Grand Ave to Fulton Ave
  • Some areas will receive waterline improvements.  Notifications will be sent ahead of water outages.
  • Areas surveyed. Fulton is being evaluated for drainage and sidewalk improvements, no construction this year.

County Road 23.5

  • Currently being surveyed.
  • Design expected to be complete in July 2016.
  • Improvements to be made 2017.
  • Project includes a regrade and drainage improvements.

South Denver

  • Design phase near completion.
  • DOLA Grant awarded.
  • Bid process begins late 2016/early 2017.
  • Estimated start early Spring 2017.

Highway 85 and Highway 52 Entrance Beautification

  • Design considerations being made.

Non-City Utility Work

To find possible construction impacts please contact the utility company conducting the work:

Century Link 1-800-526-3557
Xcel Energy at 1-800-895-4999 
United Power

CDOT Hwy85 Resurfacing